Joint venture progress report
Monday 2 Dec
2500: ordered production mold for new three-piece version of King Eagle. Sent Mongoose needed modifications to the Orion DW.
TPD: conferred with Jean regarding Traveller vs SFU telephathy.
ACTASF: Confirmed that the fleet doctrine rules will be a part of book 1.2 and apply to scenarios.
Tuesday 3 Dec
2500: Found another lost ship (K-D7C) but it needs redesign.
TPD: Jean is standing strong on including all of the species.
ACTASF: Debate continues over several issues. Tony is playtesting new rules.
Wednesay 4 Dec
2500: The quest for stands begins. Discussions of prestige scale.
TPD: Jean worked on Faz sense.
ACTASF: Tony says the new drone rules work well.
Thursday 5 Dec
2500: Green lighted Seattle
Joint venture progress report
Moderators: mjwest, Albiegamer, Scoutdad
Joint venture progress report
Business Manager/RPG Line Editor
Amarillo Design Bureau, Inc.
Amarillo Design Bureau, Inc.
- Steve Cole
- Site Admin
- Posts: 3846
- Joined: Wed Oct 11, 2006 5:24 pm
Jean doesn't know that the forum stops ready our input when it hits a Mac-based curly apostrophe. Here's the rest of the report:
THURSDAY
2500: Green lighted Seattle's jumbo freighter design.
TPD: Jean and Mike were working on psionics.
ACTASF: Tony recalculated all of the turn modes for 45 degrees.
FRIDAY
2500: Looked into the bigger minis and didn't find what I was looking for.
TPD: Lots of memos about psionics.
ACTASF: Tony has recalculated the damage scores as total FC boxes divided by 3, and says the Klingons and Kestrels gain damage score, but most cruisers stay the same.
SATURDAY
2500: Tracked down the last reports on Tholian TK5 and DN and asked Staff to release them.
TPD: psionics rules were reviewed by Mike West and Jean.
ACTASF: Reviewed Tony's outline of the changes and fixes needed and approved it.
SUNDAY
2500: Cleared the Tholian DN and TK5 to go to prototype. Tony reports receiving masters and says that the Tholian PC and CA will be easy fixes and quickly sent back to Bruce, but that the Tholian DD could take up to two weeks because of machining the joints.
MONDAY
2500: posted master status report.
TPD: Jean working on species.
ACTASF: Bill Stec pointed out a problem with ships that have thin shields and Tony said he would fix it in ACTASF1.2.
TUESDAY
2500: Seattle was getting quotes to prototype the jumbo freighter. Approved Orion BR to move to prototype.
END
THURSDAY
2500: Green lighted Seattle's jumbo freighter design.
TPD: Jean and Mike were working on psionics.
ACTASF: Tony recalculated all of the turn modes for 45 degrees.
FRIDAY
2500: Looked into the bigger minis and didn't find what I was looking for.
TPD: Lots of memos about psionics.
ACTASF: Tony has recalculated the damage scores as total FC boxes divided by 3, and says the Klingons and Kestrels gain damage score, but most cruisers stay the same.
SATURDAY
2500: Tracked down the last reports on Tholian TK5 and DN and asked Staff to release them.
TPD: psionics rules were reviewed by Mike West and Jean.
ACTASF: Reviewed Tony's outline of the changes and fixes needed and approved it.
SUNDAY
2500: Cleared the Tholian DN and TK5 to go to prototype. Tony reports receiving masters and says that the Tholian PC and CA will be easy fixes and quickly sent back to Bruce, but that the Tholian DD could take up to two weeks because of machining the joints.
MONDAY
2500: posted master status report.
TPD: Jean working on species.
ACTASF: Bill Stec pointed out a problem with ships that have thin shields and Tony said he would fix it in ACTASF1.2.
TUESDAY
2500: Seattle was getting quotes to prototype the jumbo freighter. Approved Orion BR to move to prototype.
END
The Guy Who Designed Fed Commander


- jeffery smith
- Lieutenant SG
- Posts: 190
- Joined: Wed Oct 11, 2006 5:34 pm
- Location: Bothell,WA
- Steve Cole
- Site Admin
- Posts: 3846
- Joined: Wed Oct 11, 2006 5:24 pm
- jeffery smith
- Lieutenant SG
- Posts: 190
- Joined: Wed Oct 11, 2006 5:34 pm
- Location: Bothell,WA